PUBLIC WORK DEPARTMENT
  Public Work Department is one of the major entrusted subject of BTC. This department mainly deals with construction/improvement work of roads, bridges and building works within the entire BTC area. This department is executing huge volume of works both in roads and building sector for overall development of BTC area, funded by the ministry of DONER Govt. of India under NLCPR Projects as well as annual plan scheme. This department was allocated around Rs. 1748·00 lakhs and almost all the schemes within the allocated amount is completed. Number of major RCC bridges and improvement of roads are also being taken under NLCPR Projects.

Some of the executed works under BTC for the following districts are below :

1. BAKSA :      i) Improvement of Kadamtali-Bhutankhuti Road (Namati-Mushalpur Road) heavy sand gravelling and construction of RCC hume pipe culvert N.P.-3 1000 dia repairs for the ABSU conference at Mushalpur. Estimated amount=Rs. 40·00 lakhs. Lenght=24 km. Provision : a) Sand gravelling; b) HP culvert.

                         ii) Re-construction of SPT Br., No. 3/1 on Katajhar Gharamara Road. Estimated amount= Rs. 7·84 lakhs. SPT Bridge Length=48·70 m.

Improvement of Kadamtali-Bhutankhuti
Road (Namati-Mushalpur Road)
Re-construction of SPT Br., No. 3/1
on Katajhar Gharamara Road


2. UDALGURI :  i) Improvement of Kalaigaon-Harisinga Road in T/S under PWD Udalguri Rural Road Division under Annual Plan of BTC for 2005-06. (Earth work and boulder protection work at 3rd km including earth work and gravelling from 4th to 12th km. Estimated amount=Rs. 25·00 lakhs. Length=7 km. Provision : a) Earth work in embkt. and sub-grade, b) Protection work.

                         ii) Improvement of Khairabari-Mowgaon via Mahilapara Road in T/R/S under Udalguri Rural Road Division. (Reconstruction of SPT Br. No. 1/1, 2/1 & 4/1 including approaches. Estimated amount=Rs. 25·00 lakhs. Length=9 km. Provision : a) Repairing of SPT Br. No. 1/1. b) Reconstruction of SPT Br. No. 2/1. c) New construction of SPT Br. 4/1.

Improvement of Kalaigaon-Harisinga Road
Reconstruction of SPT Br. No. 1/1, 2/1 & 4/1
including approaches

3. CHIRANG :   i) Improvement of Dwimakumari to Tilapara Ravapara (Vadragaon) Road under AOP. (Construction of wooden bridge over Kujia including temporary restoration). Estimated amount=Rs. 35·00 lakhs. Length=3 km. Provision : Construction of SPT bridge length 70 m.

                          ii) Improvement of Gwjwnpuri-Iragdao Road (Bongaigaon under AOP 2004-05) (Earth work and gravelling). Estimated amount=Rs. 10·00 lakhs. Length=1·148 km. Provision : a) Earth work in formation, b) Gravelling.

Improvement of Dwimakumari to
Tilapara Ravapara (Vadragaon) Road
Improvement of Gwjwnpuri-Iragdao Road

4. KOKRAJHAR : i) Replacement of all triple opening Hume pipe culvert No. ½ near Girls’ H.S. School by 3·00 m × 3·oo m × 12·00 m RCC Box cell culvert including approaches on Metd. Kokrajhar-Bahalpur Road. Estimated amount=Rs. 10·00 lakhs. Provision : Construction of Box cell culvert (single cell).

Replacement of all triple opening Hume
pipe culvert No. ½ near Girls’ H.S. School
Improvement of riding quality of
Kokrajhar-Ramfalbil Road

                          ii) Improvement of riding quality of Kokrajhar-Ramfalbil Road by providing BUSG on pot-holes and surfaces dressing from 1st km to 8th km including construction of RCC Box culvert. Estimated amount=Rs. 65·00 lakhs. Length=5 km. Provision : a) BUSG on pot-holes, rut depression etc. b) Pmc & seal coat. c) RCC Box culvert.

Construction of RCC Box cell bridge No. 14/3 on Dotma-Balajan Road

                          iii) Construction of RCC Box cell bridge No. 14/3 on Dotma-Balajan Road by 2·00 m × 2·00 m. Estimated amount=Rs. 8·69 (L). Provision : Construction of Box cell bridge (Triple cell).
   
 
 